Click Manufacturing Control>Inquiries> Bill of Materials Inquiry.
(Optional) Use the Go To or Starts With fields to specify the bill of material finished item number to be displayed.
In the center of the screen, select the information view to display in the lower portion of the screen. You have these options:
|
Components |
Displays component information including the component item number, description, number of units, stocking unit of measure and memo. |
|
Planned |
Displays the planned production currently in the BOM system for the finished item. Planned production is displayed in date order. Click Requirements to display the Production Planning Requirements (MCE121) program. |
|
Production |
Displays the production tickets in process for the finished item in summary. Summary information includes ticket number, status (E-entered, P-printed and C-confirmed), entry date, planned production date, production date (if not confirmed, date is blank), units planned to be produced and actual units produced. Click Line Detail to access Production Detail for the Selected Ticket (MCI613). |
|
Costing |
Displays costing information by warehouse to produce one BOM finished item. Information for each component item includes item number and description, units needed to produce the BOM finished item, stocking unit of measure, cost, costing unit of measure and extension. Total information includes components, overhead, package, labor, and total costs. Click Next Whse to view costing information for the next available warehouse. |
|
History |
Displays the history of the item. Specify the beginning warehouse. Information by warehouse includes month-to-date, year-to-date and prior year units produced and the last date produced. |
|
Requirements |
Displays the requirements for producing a number of units. Click # of Units to specify the number of units to be produced. The requirements to produce the finished item are displayed including this information for each component: the item number and a part of the description, units required, stocking unit of measure, on hand, on order and committed quantities. An asterisk (*) next to the units indicates that the number of units required is greater than available (available = on hand + on order - committed). |
|
General |
Displays additional information about the finished item, including the overhead percentage, packaging and labor costs, the update in Sales Order Entry setting for component item selection, standard packing quantity and stocking unit of measure. |
4. Click Exit.